News Date:2020-08-10 14:08:19
What are the specifications for the use of slag pots?
1. Before using the slag pots, it is necessary to confirm that there is no one on the road and there is no vehicle before operation.
2. After the slag pots is full of steel slag, the vehicle must be lifted and put down gently. When the vehicle is operating, the surrounding personnel must be called away.
3. Remember to use dry slag in the pad slag pots, not wet slag, and avoid firing.
4. Before the start of the slag tank carrier, large steel casting manufacturers must check whether the wires are damaged to prevent the wires from being exposed and electric shocks.
5. Fold the full red slag cans to ensure that the red slag cans are stored for about 16 hours in winter, and can be stored for about 24 hours in summer. It is better to extend the time, but not too long, and to ensure that it is completely solidified before folding. It can prevent the liquid slag from flowing out, causing a fire and causing a serious fire accident.
6. It is completely forbidden to fold the slag pots on a wet site or on a relatively wet object.
7. When digging the pool with cement, it is forbidden to pass over the top of the slag pool, and put the mud into the slag pool.