News Date:2017-06-27 16:36:35
Take our 600,000 t/a slag power production line as an example, the total investment of this project is RMB 50 million. It took into production on April, 2011. Within 2 years, all the investments has returned and now is benefits. The investment details list as below:
Project
|
Indicator
|
Practical operation
|
Start date
|
Date of start running
|
April 2011
|
Investment calculations
|
Total investment
|
50 million
|
Cost calculation
|
Raw material cost
|
70YUAN/T
|
Production costs(including salaries, electricity, coal, and maintenance management fees, sales charges, and so on)
|
50 YUAN
|
|
Profit calculation
|
Market sales prices
|
160 YUAN/T
|
Tons of profits
|
40 YUAN/T
|
|
Annual profit
|
40X600,000=24 million
|
|
Economic benefits
|
Within 2 years, all the investments returned (currently in a State of pure profit)
|
|
Slag powder quality
|
Fineness
|
500 m2/kg
|
7d Activity index
|
About 100%
|
|
Activity index
|
Pass GB S95
|
CUSTOMER STORIES
On 10th November, 2015, Chairman of Indonesia Growth Steel Group, came to Xinxiang Great Wall machinery co., LTD., signed about 300,000 t/a of nickel slag grinding line EPC Turkey Project contract. In May 2016 Indonesia Growth Steel Group with an annual output of 300,000 tons of nickel slag powder production line vertical mill, auxiliary, accessories, etc. sent to Indonesia;In September 2016, the Indonesian Growth Steel Group annual output of 300,000 tons of nickel slag powder production line project design, civil construction and equipment manufacturing phase has been successfully completed,Equipment installation,Commissioning work Near the end. November 3, 2016, Indonesia Su Gang Group with an annual output of 300,000 tons of nickel slag powder EPC project completed and put into production!